Production Part Approval Process
What is PPAP? - Production Part Approval Process
It is one
of the 5 core tools. (i.e. APQP, PPAP, SPC, MSA, FMEA)
It is the
Initial Process in which customer demands from supplier to perform Production Process
with specified documents / records which is for submission / review of customer
to get approval for further production.
History of PPAP
Developed
by AIAG (Automotive Industry Action Group)
With the
help of Auto giants Like Ford, Chrysler & General Motors
Initially it was limited to Automotive Industries only but
looking to its positive aspects it is now widely spread in many other
Industrial Segments.
Latest Version of PPAP is its 4th Edition w.e.f 1st
June 2006 released by AIAG.
Purpose of PPAP
To determine and provide evidence that all customer engineering design record and specification requirements are properly understood and fulfilled by the supplier organization
To
demonstrate that the manufacturing process has the potential to produce the product
consistently meeting these requirements during an actual production run at the
quoted production rate.
PPAP Document List and Submission Levels
PPAP Process Requirements
Significant Production Run
For production parts:
Product for PPAP shall be taken
from a significant production run. This significant production run shall be
from one hour to eight hours of production, and with the specific production
quantity to total a minimum of 300 consecutive parts, unless otherwise
specified by the authorized customer representative.
For bulk materials:
No specific number of “parts” is required. The submitted sample shall be taken in a manner as to assure that it represents “steady-state” operation of the process.
No specific number of “parts” is required. The submitted sample shall be taken in a manner as to assure that it represents “steady-state” operation of the process.
Now, let us understand PPAP Documents one by one:
1. Design Records
The organization shall have the
design record for the saleable Product.
If Customer is Design
Responsible, then it will be in the form of Customer Drawing
If Supplier is Design
Responsible, then it will be in the form of Supplier released drawing.
In both the cases, ballooned
printed copy of the drawing or design record should be submitted.
2. Authorised Engineering Change Documents
The organization shall have any
authorized engineering change documents for those changes not yet recorded in
the design record but incorporated in the product, part or tooling.
3. Engineering Approval
The Customer Engineering Approval
section is relatively new and was included in the latest AIAG PPAP.
Where specified by the customer,
the organization shall have evidence of customer engineering approval.
4. Design Failure Modes and Effect Analysis – DFMEA - (if applicable)
Please note that this is only
applicable when the supplier has the design responsibility.
The product design-responsible
organization shall develop a Design FMEA in accordance with, and compliant to,
customer-specified requirements.
A single Design FMEA may be
applied to a family of similar parts or materials in agreement with Customer.
5. Process Flow Diagram
The organization shall have a
process flow diagram in an organization-specified format that clearly describes
the production process steps and sequence, as appropriate, and meets the
specified customer needs, requirements and expectations
For bulk materials, an equivalent
to a Process Flow Diagram is a Process Flow Description.
Process flow diagrams for
‘families’ of similar parts are acceptable if the new parts have been reviewed
for commonality by the organization with Customer agreement.
6. Process Failure Modes and Effect Analysis – PFMEA (if Applicable)
The organization shall develop a
Process FMEA in accordance with, and compliant to, customer-specified
requirements,
A single Process FMEA may be
applied to a process manufacturing a family of similar parts or materials if
reviewed for commonality by the organization with Customer agreement.
7. Control Plan
The organization shall have a
Control Plan that defines all methods and controls used for process control and
complies with customer-specified requirements & IATF 16949:2016
requirements.
Control Plans for “families” of
parts are acceptable if the new parts have been reviewed for commonality by the
organization.
Control Plan approval may be
required by certain customers.
8. Measurement System Analysis (MSA)
The organization shall have
applicable Measurement System Analysis studies, e.g., gage R&R, bias,
linearity, stability, for all new or modified gages, measurement, and test
equipment.
For bulk materials, Measurement
System Analysis may not apply. Customer agreement should be obtained on actual requirements.
Supplier MSA system shall record
all tools and instruments used to measure or check the raw materials and
finished parts that are listed in the control plan.
Please note that the supplier’s
MSA system should conform to their relevant ISO or IATF standard.
9. Dimensional Results
The organization shall provide
evidence that dimensional verifications required by the design record and the
Control Plan have been completed and results indicate compliance with specified
requirements.
The organization shall have
dimensional results for each unique manufacturing process, e.g., cells or
production lines and all cavities, moulds, patterns or dies.
The organization shall record,
with the actual results: all dimensions (except reference dimensions),
characteristics, and specifications as noted on the design record and Control
Plan.
Dimensional results typically do
not apply to bulk materials.
10. Records of Material / Performance Tests
Material Test Results
The organization shall perform
tests for all parts and product materials when chemical, physical, or
metallurgical requirements are specified by the design record or Control Plan.
Performance Test Results
The organization shall perform
tests for all part(s) or product material(s) when performance or functional requirements
are specified by the design record or Control Plan.
Material & Performance test
results may be presented in any convenient format.
11. Initial Process Study
The organization shall use the
following as acceptance criteria for evaluating initial process study results
for processes that appear stable.
Results Interpretation
Index > 1.67 - The process
currently meets the acceptance criteria. Seek approval and start production as
per Control Plan.
1.33 ≤ Index ≤ 1.67 - The process
may be acceptable but requires some improvement.
Index < 1.33 - The process
does not currently meet the acceptance criteria.
Unstable Process:
Depending on the nature of the
instability, an unstable process may not meet customer requirements.
Processes with One-Sided
Specifications or Non-Normal Distributions
The organization shall determine
with the authorized customer representative alternative acceptance criteria for
processes with one-sided specifications or non-normal distributions.
Actions to Be Taken When Acceptance
Criteria Are Not Satisfied
Contact customer representative
if the process cannot be improved and acceptance criteria cannot be met by the
required PPAP submission date.
12. Qualified Laboratory Documentation
Inspection and testing shall be performed
by a qualified (accredited) laboratory (internal or external) as defined by
customer requirements and shall have a laboratory scope and documentation
showing that the laboratory is qualified for the type of measurements or tests
conducted.
13. Appearance Approval Report – AAR – (if applicable)
A separate Appearance Approval
Report (AAR) shall be completed for each part or series of parts if the
product/part has appearance requirements on the design record.
14. Sample Production Parts
The organization shall provide
sample product as specified by the customer.
15. Master Sample
The organization shall retain a
master sample for the same period as the production part approval records. The
master sample shall be identified as such and shall show the customer approval
date and signature on the sample. The organization shall retain a master sample
for each position of a multiple cavity die, mold, tool or pattern, or
production process unless otherwise specified by the customer.
16. Checking Aids
If requested by the customer, the
organization shall submit with the PPAP submission any part-specific assembly
or component checking aid.
The organization shall certify
that all aspects of the checking aid agree with part dimensional requirements.
When special tools are used, they
should be photographed, documented and included in this section, and this
should also include the calibration records of the tools and the dimensional
report from the tools.
17. Customer Specific Requirements
The organization shall have
records of compliance to all applicable customer-specific requirements.
18.1 Part Submission Warrant (PSW)
Upon completion of all PPAP
requirements, the organization shall complete the Part Submission Warrant
(PSW). A separate PSW shall be completed for each customer part number unless
otherwise agreed by the customer.
The organization shall verify
that all the measurement and test results show conformance with customer
requirements and that all required documentation is available and, for Level 2,
3, and 4, is included in the submission as appropriate.
18.2 Bulk Material Checklist
For bulk materials, applicable
customer-specific requirements shall be documented on the Bulk Material
Requirements Checklist.
Customer PPAP Status
Approved - Part or
material meets all customer requirements and can be shipped as per customer
schedule.
Interim Approval - Part or
material can be shipped on a limited time or piece quantity basis.
Rejected - The submission
and / or Process shall be corrected to meet customer requirements and the fresh
submission shall be approved before production quantities may be shipped.
Record Retention
PPAP records, regardless of
submission level, shall be maintained for the length of time that the part is
active plus one calendar year.
To watch video on PPAP, you can click on YouTube Plugin on this blog. There you can find video on this Topic as well as other topics too. For your convenience I am posting direct link here for PPAP Video
For videos on other engineering
topics, refer below YouTube channel.
Thanks You ….
3 Comments
guy tang titanium toner - Tatyana.com
ReplyDeleteIn this T-Shirt titanium astroneer you can get a t-shirt titanium solvent trap monocore and titanium nitride coating service near me a The T-Shirt features a T-Shirt with two titanium sia different colors of yellow and titanium oxide red.
y595u7kdhfa669 black dildos,horse dildo,masturbators,dildos,cheap sex toys,vibrators,sex chair,huge dildos,finger vibrator j947a2osecf557
ReplyDeleteed386 wholesale nfl jerseys,cheap jerseys,Cheap Jerseys from china,Cheap Jerseys free shipping,nfl jerseys,Cheap Jerseys free shipping,cheap nfl jerseys,wholesale nfl jerseys,nfl jerseys tg766
ReplyDelete